18(1)Where a claimant has not been paid an amount owing for work, material, goods or supplies in connection with a contract to which the Act applies, the claimant may give the Crown a notice of claim in writing of such amounts owing and shall include in that notice the following:
(a) specific details of the work, material, goods or supplies done or supplied by the claimant including the time, date and place of performance thereof and specific details of the claimant’s contract, change order or request under which the work or supply was performed;
(b) the amount that has been received in payment by the claimant, if any, and the amount remaining unpaid to him; and
(c) such additional information as may be requested in writing by the Crown within ten days of receipt of such request.
18(2)A notice of claim shall be given to the Crown not sooner than thirty days from the date the claimant’s contract calls for him to be paid and not later than sixty days from that date.
18(3)Any notice of claim of an amount owing shall be delivered by registered mail or by personal service
(a) to the engineer-architect of the Owner in the contract with the contractor through which the claimant provides work, material, goods or supplies,
(b) to the contractor, and
(c) where the claimant is not under contract with the contractor directly, to the subcontractor with whom he has contracted.
18(4)Every notice of claim shall be signed by the claimant or an authorized representative thereof.