Testing of detonators before firing
163Before firing a charge, a blaster shall ensure that electric detonators are
(a) tested for continuity with a blasting meter before being used,
(a.1) tested in accordance with the manufacturer’s specifications, and
(b) shunted or short-circuited after being tested until they are connected in circuits.
93-8; 2024-38
Testing of detonators before firing
163Before firing a charge, a blaster shall ensure that electric detonators are
(a) tested for continuity with a blasting meter before being used, and
(b) shunted or short-circuited after being tested until they are connected in circuits.
93-8