( a) ![]() subject to subsection (1.1), for the compilation of data from the claim maps or documents under subsection 14(4) of the Act, including abstracts of mineral claims and letters of confirmation of status of mineral claims, mining leases or rights granted under subsection 25(2) of the Act, per hour .............. | $ 50; |
| |
( b) ![]() for a transfer or assignment of a mortgage, charge or other security interest on a mining lease or on an agreement referred to in section 25 of the Act .............. | $100; |
| |
( c) ![]() for a prospecting licence under section 29 of the Act, for a natural person .............. | $100; |
| |
( d) ![]() for a prospecting licence under section 29 of the Act, for a partnership .............. | $200; |
| |
( e) ![]() for a prospecting licence under section 29 of the Act, for a corporation .............. | $500; |
| |
( f) ![]() for registering a mineral claim .............. | $10 per mineral claim unit; |
| |
( g) ![]() subject to subsection (1.2), for the work commitment security deposit .............. | $50 per mineral claim unit; |
| |
( h) ![]() for renewing each mineral claim under subsection 56(1) of the Act, first to fifth renewals, per year .............. | $10 per mineral claim unit; |
| |
( i) ![]() for renewing each mineral claim under subsection 56(1) of the Act, sixth to tenth renewals, per year .............. | $20 per mineral claim unit; |
| |
( j) ![]() for renewing each mineral claim under subsection 56(1) of the Act, eleventh to fifteenth renewals, per year .............. | $30 per mineral claim unit; |
| |
( k) ![]() for renewing each mineral claim under subsection 56(1) of the Act, sixteenth and successive renewals, per year .............. | $50 per mineral claim unit; |
| |
( l) ![]() for payment in lieu of required work in the first year of a mineral claim under subsection 56(10) of the Act .............. | $20 per mineral claim unit; |
| |
( m) ![]() for grouping 2 or more mineral claims into one group of contiguous mineral claims under subsection 58.1(1) of the Act, per resulting group .............. | $ 20; |
| |
( n) ![]() for filing a notice of dispute under subsection 61(1) of the Act .............. | $ 20; |
| |
( o) ![]() for application for a mining lease under subsection 68(1) of the Act .............. | $500; |
| |
( p) ![]() for transfer of all or part of a mining lease under section 101 of the Act .............. | $100; |
| |
( q) ![]() for transfer of all or part of a mineral claim under section 101.1 of the Act .............. | $10 per mineral claim unit. |