Acts and Regulations

91-191 - General

Full text
Testing of detonators before firing
163Before firing a charge, a blaster shall ensure that electric detonators are
(a) tested for continuity with a blasting meter before being used, and
(b) shunted or short-circuited after being tested until they are connected in circuits.
93-8